June 21, 2005

Tuesday, June 21st, 2005

The student intern work day went well. We picked up the outside of the building and started some inside cleaning too. A big thanks to the student interns and Tom.

June 21, 2005

Tuesday, June 21st, 2005

All the ruff in plumbing is done. After all the interior finish work is finished we will finish the final steps of the plumbing work by installing the fixtures.

June 17, 2005

Friday, June 17th, 2005

We have finished all the upstairs framing, including, two closets and the hall way.

June 10, 2005

Friday, June 10th, 2005

Today we finished all the downstairs framing. Next week we will finish the upstairs closets, then we will have the electrical, plumbing and hvac installed.

June 9, 2005

Thursday, June 9th, 2005

We now have the walls framed in, and can start on the details of the counters and the closets.

June 8, 2005

Wednesday, June 8th, 2005

We are framing in the new wall and securing the existing stair case.

June 7, 2005

Tuesday, June 7th, 2005

Building new walls and extending the floor joists will keep the new office area structurally sound.

June 6, 2005

Monday, June 6th, 2005

After a long anticipated meeting with the City we are back to work on the Brown house. We are framing in the ADA bathroom and finishing the stairs, hallways, closets and offices. Here we are drawing out the floor plan and fastening the floor plates to start the framing.

January 11, 2004

Tuesday, January 11th, 2005

We have insulated and put the siding back on the dormers.

January 10, 2004

Tuesday, January 11th, 2005

The gutters have been manufactured, installed, and soldered together.